The construction phase of this project is now complete.

There may still be updates, so the project will remain here. We are still monitoring the project and will reply to any comments. So if you have any questions please feel free to comment or contact us here.

EEL PROTECTION SCHEME

River Bure (Belaugh)

The Eel Regulation Compliance project at the River Bure in Belaugh is for installation of eel friendly screening equipment at our abstraction point on the river. The work is driven by the need for Essex & Suffolk Water to comply with the Eels Regulations (2009) and will improve the biodiversity value in the River Bure.

Update by ESW Project Manager

The archaeologists are still working on their final report so I'll feedback on that once we receive it.

We've continued with the civils works on site, the piling went well and the steel framework to support the new kiosk is being manufactured so will be delivered to site soon. The same team are working on a related project on the River Waveney in Suffolk so across the two sites they've made really good progress.

The attached pictures show the recent piling activity in action.