Update by ESW Project Manager
More good progress was made on site last week. The kiosk was installed first and the control equipment was placed inside on Friday. Electrical connections and testing will follow.
The infrastructure needs to be finished before the eel screens can be installed but if progress continues to remain on track the screens should be going in at the end of this month or early October. That activity will be weather-dependant as it will involve a dive team working in the river.