Update by Kevin Packard
Hi.
Work is continuing well to prepare for the arrival of our new eel-friendly bandscreen which is due to arrive on site on this coming Monday 23rd November. The structural platform is in place and the team are now carrying out electrical cabling and mechanical works to get everything in place for next week. In order to be sure that everything is ready, we will be taking the unusual step of working on site over this weekend for the first time. Our contractor IWS has assured us that there will be no heavy engineering work and will create minimal noise disturbance. The team will respect the fact that it is the weekend and a time of rest and relaxation for most people.
Thanks for your understanding as we near the completion of this upgrade project.
Cheers, Kevin