Update by ESW Project Manager
Langford Mill Eel Screen Update
The eel screen installation at the Mill has progressed rapidly in the last two weeks. The old screen structure was removed once the river was drained down allowing the new support framework and walkway to be installed in the same location. The new wedge-shaped screen was then lowered into the river and connected back to the support structure. The mesh screening panels were set in place once the main structural installation was completed.
Works continue on the electrics, controls and debris removal systems as well as peripherals like an access pathway and new fencing. Testing and commissioning starts in earnest next week (from Monday 31st January).
The attached photos show the recent progress and the screen in situ. Click on a photo for a larger view and to see the explanatory caption.