Welcome to your Community Portal

Key

General Project
Eel Protection Scheme
Every Drop Counts
Water Network Improvements

Latest Updates

By ESW Project Manager

River Blackwater Weir/Sluice Fish & Eel Pass A Planning Application has been submitted to Maldon District Council for the proposed fish and eel pass on the River Blackwater. If you’d like to view the details it can be accessed on the Maldon District Council Planning website under reference no. 22/00388/FUL (if you follow the link below you can enter the ref no. in the search bar). https://publicaccess.maldon.gov.uk/online-applications/ A decision is expected around the end of June/early July.

By ESW Project Manager

Langford Mill Eel Screen Update Finishing works on the Mill screen and surroundings are mostly complete now, the screen has passed a 28-day trial period successfully and it's now in normal operation. It will be monitored and maintained regularly by the local Operations team to make sure it continues to perform well through all seasons. An information board has been provided to the Mill House Hotel to support any queries their customers may have about the project. There are similar boards at the River Chelmer Intake and at the Langford Museum of Power, why not pop along to the museum and take a look!

By ESW Project Manager

Langford Mill Eel Screen Update The screen installation works at the Mill are complete and the screen wipe and wash system are now in operation. Optimisation adjustments and testing will continue over the next few weeks to maximise the screen's operating efficiency. Peripheral works like fencing, pathways and reinstatement of the grounds will continue for a few days but should be complete by mid-February.

By ESW Project Manager

6 Photos
Langford Mill Eel Screen Update The eel screen installation at the Mill has progressed rapidly in the last two weeks. The old screen structure was removed once the river was drained down allowing the new support framework and walkway to be installed in the same location.  The new wedge-shaped screen was then lowered into the river and connected back to the support structure. The mesh screening panels were set in place once the main structural installation was completed. Works continue on the electrics, controls and debris removal systems as well as peripherals like an access pathway and new fencing. Testing and commissioning starts in earnest next week (from Monday 31st January). The attached photos show the recent progress and the screen in situ. Click on a photo for a larger view and to see the explanatory caption.

By ESW Project Manager

Langford Mill Eel Screen Update The installation works have started on site this week so if you're in the area you may notice our contract team busy in and around the Mill building. The majority of the works this week have been inside the Mill working on the electrical installation whcih will continue into next week. The screen fabrication team will be on site next week to start assembling the screen itself. The installation into the river is planned for the week beginning Monday 17th January, weather permitting. We will be working with the EA Fisheries team again to safely lower the river level and make sure any fish in the vicinity are protected. Lowering the water will allow the screen to be set in place without the need for divers working underwater.

By Stef Chester

Happy New Year! Between September and Christmas, our teams have been out in the area checking for, and repairing, leaks where possible to reduce the amount of water wasted from our pipework. We’ve been using satellite imaging and new technology to help us do this, and we plan to continue using these throughout the rest of the project to make sure we save every drop we can. Our teams have also been quick to respond to leaks in customer homes and we’ll continue to help where we can, so if you think you might have a leaking toilet, or a leak elsewhere in your home, please get in touch with us to see if we can help. To report a leaking toilet and to find out if we can fix it for free, you can get in touch with us online here, call us for free on 0800 953 0130 or email watersaving@nwl.co.uk We were out and about in a number of the local villages and towns to raise awareness of our initiative and you may have seen our posters or postcards on local noticeboards or in community hubs. We’re looking forward to continuing the conversation with you at community events over the next eight months and, once we have a better idea of government restrictions, we’ll be sharing the events we’ll be attending over the spring and summer on here and on our ‘Planned Event’s page. We also launched our nomination form for community groups and charities in December. You know your patch better than anyone else and that’s why we’re asking you to nominate charities and community groups that support critical issues that are close to our heart and would benefit from the funding available. You can nominate charities or community groups here. The more water that you help us save, the more funding will be available for projects in your area. With colder weather forecasted, you might notice more leaks when you’re out and about so please do report any leaks you see, you can report them online here or, if you’ve found a serious leak, you can call our emergency leakline on 0800 526 337. You can also do your bit and raise funds for your community by using water wisely throughout the day both in and outside of your home, click here for water saving tips or to use our virtual water efficiency assistant. And if you don’t have a water meter, it might be worth looking into getting one fitted. Having a water meter allows you to become more aware of your usage, and the less you use, the less you pay. Check out our water usage calculator here to see if you could save money with a water meter and you can also apply online to have one fitted. We’re looking forward to working with you in 2022!

By ESW Project Manager

Langford Mill Eel Screen Update Works on the Langford Mill eel screen are continuing to progress well. The lowering of the river for inspection of the area was successful and fish protection was maintained throughout. Due to this success, the project team are now planning to lower the river level again for the installation of the eel screen rather than having dive teams working in the water as was originally designed. These works are scheduled for mid-late January 22, assuming weather conditions are suitable and the river is not in flood. Most activities on this project are happening off-site for now; manufacture of the eel screen has been completed and the support structure and control systems are also being built off-site. There are likely to be some minor preparatory works in and around the Mill in the lead up to Christmas but the main site works will commence in the New Year.

By ESW Project Manager

Langford Mill Eel Screen Progress Activities on the Langford Mill Eel Screen project are taking shape. This week the team have been preparing the site, installing temporary fencing and levelling the ground to create a safe working area next to the river. We had an archaeologist on site with the team today overseeing the levelling works in case of any historically important finds although nothing of interest was turned up. Preparations are being made for the lowering of the river to enable the existing intake structure to be inspected. We're working closely with the Fisheries team from the Environment Agency to make sure fish are protected during these works. The EA will monitor the activity, checking the oxygen levels in the water and will assist with moving fish out of the affected area if required. It's hoped that this will all take place next week (from Monday 27th September), pending receipt of a permit from the EA. Further updates will be provided if the works have to be rearranged. In addition to these site-based works, the eel screen fabrication is progressing well at the manufacturer’s workshop. When complete, it will be transported to site in sections and reassembled at the riverside before being lifted into place with a crane.

By Harriet Morrison

Hi and thanks for visiting our community portal for our Water's Worth Saving initiative. My name is Harriet and I’m the Customer Engagement Advisor for Essex & Suffolk Water. I’ll be providing updates on behalf of the Water's Worth Saving team throughout the duration of the scheme so please remember to check back regularly to follow our progress.   This area of Suffolk is our focus, due to challenges faced with supply and demand, whereby the combination of repeatedly warm, dry weather spells, more people holidaying in the area, and more people working from home during the Coronavirus pandemic has resulted in an increase in the use of water.    The amount of water available for us to treat in this area hasn’t increased, it has and will stay the same. We can’t take any more water away from the surrounding environment. That’s why it’s so important that we work together to reduce any water wastage and unnecessary use, to make sure our teams can keep up with the demand.   We are excited to bring this opportunity to this area of Suffolk and can’t wait to dive right in and succeed with the local community. Our plan is to work together with local groups, schools, charities, and residents to protect local water resources. I’ll share more information here soon about our plans to attend community events and I’d love to see you there and have a chat. I’ll also be available to talk over Zoom or Teams on a regular basis, and we'll also be holding frequent digital discussion groups, the details of which will be posted in due course.  Want to get involved and raise funds for your community? Play your part by:  Reporting any leaks seen out and about via our leakage portal.  Reduce the amount of water wasted throughout the day in your home/community.  Repairing leaking toilets and be on the look out for leaking toilets.   And don’t forget, if you haven’t got a water meter, having one fitted also allows you to become more aware of your usage, and the less you use, the less you pay.  Sign up here to receive a quarterly newsletter.

By ESW Project Manager

The Blackwater fish and eel pass project at Langford is also progressing. The outline design for the pass has been approved by the Environment Agency and is now moving into final design development for the construction phase. The pass will be located at the southern end of the existing weir structure approx. 130m upstream of Langford Mill. The attached General Arrangement drawing shows the location and proposed layout for illustrative purposes.

By ESW Project Manager

Langford Mill Eel Screen Works Commencement We have engaged Farrans Construction for the installation phase of the Langford Mill Eel Screen project and preparations are being made to enable works to start on site at the beginning of September. Initial site mobilisation activities will include setting up of welfare cabins and preparing the ground with temporary hardstanding for the working area. The grounds will be returned to grass once the site works are finished. The screen is currently being manufactured off-site and is expected to be delivered for installation in November. Whilst the screen is being fabricated, preparatory works on site will include surveys and inspections (including a 2-3 day lowering of the river level to enable inspection of the existing concrete structure), installation of an access platform, a pathway and electrical works inside the Mill building. The scheduled site completion for the Mill Eel Screen is February 2022. As described in the section on Planned Work, there are two further associated projects in this area so there is likely to be a continuing construction site presence beyond the February end date for the Mill. As the plans for the other works are developed more details will be shared here on the portal in future updates.

By ESW Project Manager

Site Layout and Construction Development for the Langford Mill Eel Screen Plans are developing now for the installation phase of the Langford Mill Eel Screen project. Currently works are expected to start on site around August 2021. The drawing below shows how the site will be laid out once the installation is complete. The main elements to be constructed are marked ‘new’ on the drawing. During construction, the site will be fenced off (as indicated by the dotted red line) to maintain a safe working area separated from any passers-by. The maintenance platform, pathway and control systems inside the Mill building will be constructed first whilst the screen is manufactured off-site. When the screen is delivered for installation there is likely to be a crane on site for a short time to lift it into the river but for most of the time the site presence will be a few construction engineers and smaller vehicles. Our vehicles will access the site via the existing double gates off the B1019 Maldon Road (between the Mill and the village Hall). There are no road closures or long-term traffic lights anticipated to support the access arrangements but there may be occasional short duration traffic controls to enable larger vehicles to safely navigate the entrance. More details will become available on traffic management once the construction plans are in place.