Update by ESW Project Manager
Works on the Fish Pass and Eel Screens on the River Blackwater are progressing, the main contractor for the Fish Pass installation has been appointed and they are planning to undertake some pre-start surveys during the next 3-4 weeks, with the aim of mobilising to begin construction in August. More updates will follow as dates are firmed up.
Detailed designs for the new eel screens for the Blackwater Intake are almost complete which will enable the planning application for the works to be submitted, hopefully also in August. You may have noticed a bit more activity in the area recently as we've been carrying out several surveys for ecology, arboriculture and constructability, as well as making plans for a new access track and power supply. If planning permission is achieved the main construction works for this project will begin in 2024.