Update by ESW Project Manager
Fish & Eel Pass Progress Update, September 23
The fish pass team have been on site for about a month now and have achieved great progress. The site is all setup, the trackway for access has been installed, tree stumps removed and protective fencing has been placed around the trees that are remaining to make sure vehicles can’t encroach into their root protection zones.
This week we have started to install a ‘portadam’ in the upper river and the lower pond which will provide a dry working area, enabling the team to start excavating to create the trench where the fish pass will be inserted. We’ll have an archaeologist on site next week observing the excavation works to see if there are any interesting historical artifacts uncovered.
The attached photos show the trackway, tree protection fence and the installation process for the portadam.