Update by ESW Project Manager
We haven't had the full report back from the archaeologists yet but Norfolk County Council have reviewed it and given us the green light to continue with the piling works next week. The piles have been re-sited so they won't interfere with the flint wall in any way. The piling is now planned for Thursday 16th and Friday 17th.
This week the team have continued on grounds preparation works and installing some ducting. They had a fabulous view of the river today with the sun perfectly placed for a mirror effect. There are definitely worse places to work!