GENERAL PROJECT

Layer to Langford Pipeline

To ensure Essex & Suffolk Water (ESW) can continue to provide a reliable and resilient supply of water to its 1.5 million customers in Essex, it is looking to improve the raw water transfer capacity between its operating areas. To achieve this ESW are intending to construct a pipeline to transfer raw water from Layer-de-la-Haye Water Treatment Works to the existing storage reservoir at Langford Water Treatment Works.

Project updates

Update by Daniel Wilson

You may have seen our teams working alongside the B1026 near to Abberton Reservoir over the last few weeks. This team has begun to install the 900mm diameter pipeline that we have been receiving from our suppliers over the last few months. Its here that the water conveyed by the pipeline begins its journey south towards Langford WTW.

We also welcomed BBC Essex on the 24th April who were keen to see what we were up to, talk to our installation teams and out Water Director, and to then go on into Colchester to discuss Smart Meters with local residents. IT was a great experience for the project team and nice to show off this fantastic project to improve water resilience in Essex.

Please Login in order to comment on this update.

Update by Daniel Wilson

Despite the very wet start to the year our construction teams have been working hard to begin pipelaying activities along the pipeline route. We previously posted an update about the progress of topsoil stripping and whilst this continues, we are also starting to put pipe into the ground. This work has started at our Langford WTW, adjacent to the Museum of Power. We recently completed the connection of two of the mains we had previously installed under the River Blackwater and we are now laying away from these towards the Water Treatment works. 

In late March we will also being our archaeological mitigation work, having completed the trial trenching last year. The mitigation works will allow the archaeological teams to further understand the history of the area that our pipeline crosses. In total we have 21 areas where the local authorities would like us to complete further investigation work. These range from small area circa 20m in length up to areas that are 500m in length. 

Please Login in order to comment on this update.

Update by Daniel Wilson

Work started this week to strip the topsoil along the route of the Layer to Langford Pipeline in anticipation of the pipe deliveries being made to site later in February. The topsoil is stripped by large excavators and/or bulldozers which pile up the topsoil on one side of the working area. When we come to excavate the trenches within which the pipe will be laid, the subsoil will be kept seperate from the topsoil to ensure the land is reinstated in the way it was found. The work has started at the Layer Water Treatment Works end of the pipeline and will move south over the next few months towards the other end of the route at Langford Water Treatment Works.

Last week we also completed what is called a 'strategic connection' onto an existing water main. At this strategic connection we will install valves that will help us to divert water into the new pipeline. 

Please Login in order to comment on this update.

Update by Daniel Wilson

The project has achieved a number of major milestones this year. We have now completed all of the planned road crossings along the route, we have completed the directional drill work beneath the River Blackwater and the Langford Cut, and completed our archaological and ecololgical mitigations. This puts us in a fantastic position to start the pipelaying in early 2024. Below are a few photos of our activities over the last year on the project. 

Please Login in order to comment on this update.

Update by Daniel Wilson

Our Layer to Langford Pipeline Project team is using a non-intrusive method to cross two major Rivers in Essex, the River Blackwater and the Langford Cut.

The method, known as directional drilling, drills a tunnel beneath the rivers through which over 200m of pipeline will be pulled. The alternative to this would involve sheet piling the rivers to stop the flow, overpumping the water and then open cutting the rivers, potentially causing ecological and environmental disturbance.

Work started last week, beginning with the drilling of a pilot tunnel 6m beneath the river beds. This will be followed by work to widen the tunnel ready to accept the large diameter pipeline.

The drilling process itself is expected to take four weeks.

 

 

Please Login in order to comment on this update.

Update by Daniel Wilson

Today marked a significant milestone on this project with the start of our archaeological field work. Having previously completed desk based assessment and aerial surveys we have now moved into the phase of trial trenching. This involves the excavation of strip trenches across the pipeline route that will allow archaeologist to search for historic artefacts. During this phase we will be liaising closely with Essex County Council and Colchester City Council to report our findings and allow them the opportunity to complete their own assessment within the trenches. If any artefacts are located these are recorded and the trench is backfilled. Where significant artefacts are found more detailed investigation will be completed prior to the process of pipelaying, these may even alter the route of the pipeline. This phase of the work is scheduled to last approx. 8 weeks.

Please Login in order to comment on this update.

Update by Daniel Wilson

In mid April 2023 we completed the installation of the first sections of pipe associated with the project. The pipe was installed adjacent to the existing B1019 Langford Road near to the area of a new development by Countryside Properties. We worked closely with Maldon District Council and Countryside Properties to complete this work such that when the B1019 is realigned, we would not have to dig up the new road causing inconvenience to the local communities. 

Please Login in order to comment on this update.

Update by Daniel Wilson

Proposed raw water main route drawings - I wanted to share with visitors to the community portal the proposed route alignment for our new raw water main. The proposed route has been developed following extensive ecological surveys, engineering considerations and land owner engagement. We welcome your feedback on the route and any observations you may have. We will of course be happy to share the output of our surveys and investigations and many of these will support our forthcoming EIA Screening request to both Colchester Borough Council and Maldon District Council.  

Please Login in order to comment on this update.

Update by Daniel Wilson

Our Framework Partner Allied Exploration and Geotechnics (AEG) has been completing Ground Investigation work along the route of pipeline in recent weeks. This work includes an assessment of ground conidtions through which the proposed pipeline will be routed. The work is carried out using specialist equipment to drill holes up to 15m in depth into the ground to determine the underlying conditions and ensure the ground is suitable for the pipeline. 

Please Login in order to comment on this update.