Layer to Langford Pipeline

To ensure Essex & Suffolk Water (ESW) can continue to provide a reliable and resilient supply of water to its 1.5 million customers in Essex, it is looking to improve the raw water transfer capacity between its operating areas. To achieve this ESW are intending to construct a pipeline to transfer raw water from Layer-de-la-Haye Water Treatment Works to the existing storage reservoir at Langford Water Treatment Works.

Update by Daniel Wilson

In mid April 2023 we completed the installation of the first sections of pipe associated with the project. The pipe was installed adjacent to the existing B1019 Langford Road near to the area of a new development by Countryside Properties. We worked closely with Maldon District Council and Countryside Properties to complete this work such that when the B1019 is realigned, we would not have to dig up the new road causing inconvenience to the local communities. 