Update by Daniel Wilson
The project has achieved a number of major milestones this year. We have now completed all of the planned road crossings along the route, we have completed the directional drill work beneath the River Blackwater and the Langford Cut, and completed our archaological and ecololgical mitigations. This puts us in a fantastic position to start the pipelaying in early 2024. Below are a few photos of our activities over the last year on the project.