Update by David Mortemore
Good morning everyone, I hope you're all well. After making very good progress along the field edge we are now approaching the stage of having to install the new water within the road edge. This as previously communicated will require us to work within temporary two-way traffic lights for the safety of our workforce and the public passing by us. This work is expected to commence on Friday 21st with excavating the launch and reception holes for the guided boring pipe installation starting on Monday 24th February. Please get in touch if we can help any further.