Update by Sophie Saunders
Work was completed on time crossing the 5 way multi traffic light junction, the temporary traffic lights were taken down Saturday 27th October at 2pm.
From Monday 29th October we have now progressed into the Phase 4 Beccles Road to Crab Lane road closure.
The team on site this week have been erecting the fencing to enable to complete trial holes at various locations to determine the route of the new main.
The carriageway will be planed today so excavation can start as soon as possible, photos attached of the road closure and the carriageway.