The construction phase of this project is now complete.

There may still be updates, so the project will remain here. We are still monitoring the project and will reply to any comments. So if you have any questions please feel free to comment or contact us here.

WATER NETWORK IMPROVEMENTS
CURRENT WEATHER
2°C

Beccles Road, Bradwell, 450mm Water Main Installation

The overall scheme involves the installation of 4.8km of new water main and the construction of a new booster pumping station at our Lound Water Treatment Works. The scheme will increase the capacity of our existing water network in the area allowing us to provide a more efficient service to our customers.

Update by Sophie Saunders

Work was completed on time crossing the 5 way multi traffic light junction, the temporary traffic lights were taken down Saturday 27th October at 2pm.

From Monday 29th October we have now progressed into the Phase 4 Beccles Road to Crab Lane road closure.

The team on site this week have been erecting the fencing to enable to complete trial holes at various locations to determine the route of the new main.

The carriageway will be planed today so excavation can start as soon as possible, photos attached of the road closure and the carriageway.