The construction phase of this project is now complete.

There may still be updates, so the project will remain here. We are still monitoring the project and will reply to any comments. So if you have any questions please feel free to comment or contact us here.

WATER NETWORK IMPROVEMENTS
CURRENT WEATHER
8°C

Beccles Road, Bradwell, 450mm Water Main Installation

The overall scheme involves the installation of 4.8km of new water main and the construction of a new booster pumping station at our Lound Water Treatment Works. The scheme will increase the capacity of our existing water network in the area allowing us to provide a more efficient service to our customers.

Traffic Information

The current programme for the road closure is as follows:

Phase 1: 17th September 2018 to 3rd October 2018. Beccles Road closed from junction with Burnet Road to Primrose Way.

Phase 2: 3rd October 2018 to 20th October 2018 Beccles Road closed from junction of primrose Way to Chruch Lane.

Phase 3: 20th October 2018 to 29th October 2018, Beccles Road closed while the 5 way lights crossing takes place.

Phase 4 & 5: 29th October 2018 to 20th January 2019:

Phase 4: Beccles Road closed between junction of Mill Road to Crab Lane.

Phase 5: Beccles Road closed between junction of Crab Lane to Mallard Way.