Update by Sophie Saunders
Since phase 4 started on Monday 29 October there has been approximately 200 metres of 450mm ductile pipe laid and as shown in the attached photos. The trench has been back filled ready for concreting later today, once cured the black hot rolled asphalt will be carried out for the permanent finish.
Second photo shows the pipe within the barriers ready for installation when required.