Update by Sophie Saunders
The team on site are still working extremely hard. Phase 4 finished at midday on Wednesday 14 November with the road closure coming off at midday. The phase 5 road closure has been set up from Beccles Road/Crab Lane junction to Mallard Way.
Phase 4 total length of 450mm ductile iron pipe was 375 metres.