The construction phase of this project is now complete.

There may still be updates, so the project will remain here. We are still monitoring the project and will reply to any comments. So if you have any questions please feel free to comment or contact us here.

WATER NETWORK IMPROVEMENTS
CURRENT WEATHER
5°C

Beccles Road, Bradwell, 450mm Water Main Installation

The overall scheme involves the installation of 4.8km of new water main and the construction of a new booster pumping station at our Lound Water Treatment Works. The scheme will increase the capacity of our existing water network in the area allowing us to provide a more efficient service to our customers.

Update by Sophie Saunders

The team on site are still working extremely hard. Phase 4 finished at midday on Wednesday 14 November with the road closure coming off at midday. The phase 5 road closure has been set up from Beccles Road/Crab Lane junction to Mallard Way.

Phase 4 total length of 450mm ductile iron pipe was 375 metres.