The construction phase of this project is now complete.

There may still be updates, so the project will remain here. We are still monitoring the project and will reply to any comments. So if you have any questions please feel free to comment or contact us here.

GENERAL PROJECT
CURRENT WEATHER
9°C

Heybridge

Over the winter of 2017/18, Essex & Suffolk Water, in partnership with Essex Waterways, will be replacing the sea lock gate and central timber mitre gates at Heybridge Basin in Essex. The project will involve the closing and draining of the lock in October 2017, crane lifting operations for the gates and the assembly and testing of the new gates prior to the re-opening of the lock in March 2018. There will be disruption in the area during this work period but we will endeavour to keep this to an absolute minimum.

Project updates

Update by Ryan Lloyd

Hi everyone

Thank you very much for your patience especially over the last couple of days during the installation of the new timber mitre gates. The works attracted quite a crowd at one point!

It was a pleasure to witness firsthand the craftsmanship and skill that has gone into manufacturing and installing the new gates. There's still a bit of work to be done to complete the site installation but thank you to Nigel Lord and his team of Hargreaves Lock Gates for their efforts on site.

Thanks

Ryan 

 

Please Login in order to comment on this update.

Update by Ryan Lloyd

Good morning

There will be a crane on site on Tuesday the 21st of February and Wednesday the 22nd of February which will be moving both the new Wooden Lock Gates from their storage location to their final position in the Lock.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

We anticipate that for up to two hours at a time, starting at 9 AM on Both Days, we
will have to block the small access road down the side of our compound and the
road up towards the boats, there may be periods of short interruptions of no more
than ½ hour at a time when the crane is being manouvered that partial closures will
occur.

We apologise for any inconvience this may cause

Thank you

Ryan

Please Login in order to comment on this update.

Update by Ryan Lloyd

Hi everyone

In the next couple of months, there will be an increase in site activity to install the various elements for the new gates.

With the cold temperatures, tidal surges and working around the low tide times, we have had to work on a bit later than planned for on some evenings. Please accept my appolgies for any disturbance caused.

Moving forward, we hope to be back to normal working hours from the 6th Feb 2017.

Installation of new timber mitre gates 

The plan to install the new timber gates is during the week commencing 20th February 2017. Please be aware that there will be a crane on site for these works but we will endeavour to keep disruption down to a minimum. More detailed information regarding days/times will be shared in the next couple of weeks.

Best regards

 

Ryan

 

Please Login in order to comment on this update.

Update by Ryan Lloyd

Hi all

We will be removing some of the timber sleeper boards off site which were used for the crane works. There may be some road access restrictions between 10:30am - 12:00pm tomorrow 8th December 2016. However, we're trying to get this done without any access restrictions and we apologise in advance for any disruption we may cause. We really value your patience and understanding.

Thanks again

 

Ryan

 

 

Please Login in order to comment on this update.

Update by Ryan Lloyd

Good morning all

Just a quick update to share a key milestone on the project. The old upstream timber mitre gates have now been removed, allowing for the lock to be prepared for the installation of the new set of gates. It was an impressive sight seeing the old gates being lifted out with each leaf weighing in at around 6.5 tonnes! 

Thanks

Ryan

 

Please Login in order to comment on this update.

Update by Ryan Lloyd

Hi all

Just a reminder for all our residents and visitors to site for the works taking place starting tomorrow, Tuesday 6th December 2016.

There will be some restrictions to vehicle access at times tomorrow Tuesday 6th December and Wednesday 7th December between 08:30hrs and 17:00hrs for works on the upstream timber gates.

 

A crane is required for the work but the access road will not be closed for the full period but intermittently during these times when required for our setup.Please be assured we shall do everything we can to minimise any disruption during this period.

Thanks again for all your support

Ryan

 

 

 

Please Login in order to comment on this update.

Update by Ryan Lloyd

*CHANGE OF PROGRAMME FOR TIMBER GATES WORK*

Please note, the dates have now changed.

The crane works will not start until the 6th December 2016 to remove the timber gates. Another update will follow next week.  

Therefore, there will not be any restrictions for vehicle access next week 21st to 25th November. Apologies for any inconvenience caused.

Have a good weekend all

Ryan

 

Please Login in order to comment on this update.

Update by Ryan Lloyd

Good morning all

The project is progressing well and the site is due to become a hive of activity!

We will be carrying out some removal work on the timber mitre gates at the upstream end (boat basin end) of the lock from the 21st November 2016.

The work will require some crane lifts and there will be restrictions on vehicle movements during these periods;

Tuesday  22nd November (low tide about 12.30) – crane in position from about 9.30am-3pm

Wednesday 23rd November (low tide about 13.45) – crane in position from about 10.30am-4pm

We shall endeavour to minimise the distruption during this time and will provide updates if the proposed dates/times change.

Thank you for your support and understanding.

Ryan

 

Please Login in order to comment on this update.

Update by Ryan Lloyd

Hi Everyone

Apologies for the late notice, there will some more vehicle restrictions tomorrow from 10am to complete the piling at the boat basin end of the lock. We will endeavour to minimise the disruption as far as possible.

Please note, the previous update is now incorrect so there will be vehicle access between 8am - 9am. 

Thank you

Ryan   

Please Login in order to comment on this update.

Update by Ryan Lloyd

Hi everyone

The upstream piling at the end of the lock is progressing and the planned completion is for this Friday 4th November.

Please note that there may be some restriction on vehicle access at the upstream end of the lock (boat basin end) to remove some equipment this Friday 4th November between 8:00am and 9:00am.  

Thank you again for your support and apologies in advance for any distruption caused.

Ryan

Please Login in order to comment on this update.