To ensure Essex & Suffolk Water (ESW) can continue to deliver excellent quality water, we are planning the replacement of our sandwashing plant at Layer Water Treatment Works. The new sandwasher will be located in a new purpose-built yard to the west of the existing site.
The Layer Sandwasher Replacement project is the first part of a £25 million investment programme at the Layer Treatment Works to ensure that we continue to deliver excellent quality water to our supply area.
The site has an existing Sandwasher which is many years old and requires replacement. The replacement sandwasher will be installed in a new purpose-built yard in the field to the west of the existing treatment works.
Aerial view of site showing field to west
Existing sandwasher
3D image of new sand yard
The proposed plan can be viewed here Proposed Site Plan
The programme is as follows
Archaeological survey work and ground investigations June 2022
Finalise the design November 2022
Submission of planning application December 2022
Construction start June 2023
Complete construction December 2023