GENERAL PROJECT

Layer WTW Enhancements

To ensure Essex & Suffolk Water (ESW) can continue to deliver excellent quality water, we are planning the replacement of our sandwashing plant at Layer Water Treatment Works. The new sandwasher will be located in a new purpose-built yard to the west of the existing site.

Planned Work

The Layer Sandwasher Replacement project is the first part of a £25 million investment programme at the Layer Treatment Works to ensure that we continue to deliver excellent quality water to our supply area. 

The site has an existing Sandwasher which is many years old and requires replacement.  The replacement sandwasher will be installed in a new purpose-built yard in the field to the west of the existing treatment works.

       Aerial view of site showing field to west

       Existing sandwasher                                                                               

  3D image of new sand yard

 

The proposed plan can be viewed here  Proposed Site Plan

 

The programme is as follows

Archaeological survey work and ground investigations     June 2022

Finalise the design      November 2022

Submission of planning application   December 2022

Construction start    June 2023 

Complete construction     December 2023