EEL PROTECTION SCHEME

River Stour (Brantham)

The Eel Regulation Compliance project at Brantham will comprise the installation of eel friendly screening equipment at our abstraction point on the river Stour. The work is driven by the need for Essex & Suffolk Water to comply with the Eels Regulations (2009) and improving the biodiversity value in the river Stour.

Start Date

March, 2017

Estimated End Date

July, 2017

Contractor

ESW

Update by Dan Wilson

Work is well underway on site now and our contractors IWS have set up offices and storage cabins that will be on site for the duration of the work. We have also completed the excavation for the concrete slab on top of which will sit our green GRP kiosk housing the control panel for the new screen. Other work on site has included the excavation and duct laying for the new power cable between the access gate and the new kiosk.

Unfortunately we have also had a break in on site. Thieves broke into our storage cabin and stole a small portable generator and a disc cutter. We have increased security on site and remain vigilant.

Please Login in order to comment on this update.

View all updates
Rate this project

Rate this project

We would love to hear your feedback on this project.

There was an error saving your answers. Please try again.

Saving your answers.
Please wait.

Your answers have been saved. Thankyou for giving us your feedback.

1. Do you feel that our Community Portal has helped to keep you informed about our work?

2. How likely is it that you would recommend our Community Portal to a friend or colleague?

3. How likely is it that you would recommend Essex and Suffolk Water to a friend or colleague?

4. Do you have any suggestions to improve our Community Portal? Optional